Installation day itself is short: scaffold goes up the day before, and our engineers fit the panels, inverter and any battery in one to three days. Most of the work happens earlier, in the survey, the design and the grid paperwork, and a little happens afterwards, when the certificates arrive and export payments are set up. Here is the whole sequence, and what you need to do at each stage.

Before the scaffold: survey, design and DNO approval

Every project starts with a survey. We look at the roof structure, shading, the condition of the tiles or slates, where the inverter and battery can go, and the state of your consumer unit (the fuse box). We use drone imaging, so nobody needs to climb onto the roof at this stage.

From the survey we produce a design: panel layout, expected annual generation, inverter and battery choice, and a fixed quote. Most homes need no planning application. Our guide to roof suitability covers what we check, and planning permission for solar panels explains the exceptions.

The step that most often sets the date is the DNO. Your Distribution Network Operator runs the local cables and substations (in London and much of the Southeast that is UK Power Networks), and it must know about anything that can export electricity to its network. There are two routes:

  • G98: for small systems with an inverter output of up to 16 amps per phase. We connect first, then notify the DNO within 28 days of commissioning.
  • G99: for anything larger. We apply before installing and wait for approval. For a home this usually takes four to eight weeks, and commercial applications can take longer where the local network is busy.

Worked example: does your system need G99?

Sixteen amps at the UK's nominal 230 volts is 16 × 230 = 3,680 watts, or 3.68 kW. A house on a single-phase supply with a 3.6 kW inverter sits just under that line and can go through G98. A 6 kW hybrid inverter is above it, so we apply under G99 before fitting anything, which is why many home systems with batteries are booked several weeks after the survey. A business on a three-phase supply gets 3 × 3.68 = 11.04 kW before G99 applies.

Scaffold, roof work and electrical work

Scaffold goes up the day before we start and usually takes a few hours. The scaffolders need clear access to the walls shown on the design, so move cars, bins and garden furniture away from them. If the scaffold has to stand on a neighbour's land or the pavement, we arrange the permission or licence in advance and tell you what has been agreed.

On the day, we need access to the loft, the consumer unit and the spot where the inverter and battery will live, usually a garage, utility room or loft. Clear a path to each, and tell us about pets, alarms and anyone working from home.

On installation day the roof team starts early. On a pitched roof they lift tiles or slates at each fixing point, fix aluminium roof hooks to the rafters, and relay the tiles so water still runs past each hook. Rails go onto the hooks and the panels clamp onto the rails. In-roof systems replace a section of tiles with a flashing tray instead, so the panels sit flush.

Meanwhile the electrician mounts the inverter and battery, runs cable from the roof, and fits isolators so every part of the system can be switched off safely. The last job is connecting to your consumer unit. That is the only time your power is off, and in our experience it is usually one to three hours. If you work from home or rely on medical equipment, tell us at the survey and we will plan the timing around you.

Businesses usually cannot accept any disruption, so we plan around operating hours. At the artisan bakery in Peckham, where the ovens run from 4am, we split a 24 kW flat-roof install across three overnight shifts so the roof was never worked on while the ovens were running. The ballasted frame meant no roof penetrations at all.

Commissioning and switch-on

Before anything exports, we test it. The electrician measures insulation resistance, string voltages and polarity, checks the earthing and isolators, and confirms the inverter's protection settings meet the DNO's requirements. Only then do we switch on and watch the first generation figures come through.

We then set up the monitoring app on your phone and walk you through it: live generation, what the house is using, battery charge, and how to spot a problem. We also show you where the isolators are and how to shut the system down safely. The scaffold comes down shortly afterwards, usually within a day or two.

Your handover pack and paperwork

The paperwork proves the system is safe, compliant and eligible for export payments. Keep it with your property documents, because a buyer's solicitor will ask for it when you sell. A complete handover pack includes:

  • MCS certificate: confirms the system was designed and installed to the Microgeneration Certification Scheme standard. MCS installers must issue it within 10 days of commissioning.
  • Electrical Installation Certificate: records the electrical tests against the wiring regulations, BS 7671.
  • Building Regulations compliance certificate: for the notifiable electrical work, issued through the installer's competent person scheme.
  • DNO confirmation: the G98 notification or the G99 approval.
  • Warranties and datasheets: for the panels, inverter and battery, plus our workmanship warranty.
  • Performance estimate and maintenance guide: the modelled annual generation and what the system needs over its life.

Finally, we register the system for the Smart Export Guarantee (SEG), the scheme that pays you for electricity you send to the grid. It needs the MCS certificate and a smart meter that records exports. Our guide to the Smart Export Guarantee explains how rates compare between suppliers.

How long the whole process takes

Add the stages together and a typical home project looks like this, at the time of writing:

  • Survey to design and quote: about one week.
  • DNO: nothing to wait for under G98, usually four to eight weeks under G99.
  • Scaffold and install: one day of scaffolding, then one to three days of work.
  • Certificates and SEG: the MCS certificate within 10 days, then SEG registration, which depends on the supplier.

So a small G98 system can be generating two to three weeks after the survey, while a larger home system with a battery on the G99 route is more often six to ten weeks from survey to switch-on. Commercial projects take longer, mainly because of the grid application.