Business
Primary school, Croydon
A two-form-entry primary school where the headteacher wanted lower bills and a live teaching tool. We installed 60 kW over the summer holidays and put the generation dashboard on a screen in the school hall.
At a glance
The brief
Ashburton Grove Primary had seen its energy bill double in two years and was cutting back on after-school clubs to cover it. The headteacher had two asks: bring the bill down, and give the children something they could actually see and learn from.
The work had to fit inside the six-week summer holiday with the site handed back spotless for September.
The system
The 1970s flat-roof blocks were ideal for a ballasted array, and we used the sports hall roof for the bulk of the capacity. A 40 kWh battery stores lunchtime generation for the after-school period and the site's evening lettings.
We installed a large display in the entrance hall showing live generation, the day's total, and a running count of equivalent kettles boiled, which the Year 5 class now updates in their maths lessons.
- 140 × 430 W panels on ballasted flat-roof frames
- Three-phase inverters with per-block monitoring
- 40 kWh battery for after-school and lettings demand
- Public generation display in the entrance hall
The result
The school's electricity bill fell by 57% in the first academic year, which funded the return of three after-school clubs. Generation of 52,000 kWh was within 3% of our model.
The generation display has become part of the school day, and the school won a borough sustainability award for the project.
The children check the kettle counter every morning before the register. That was never in the brief, and it's my favourite part